Key Investor Takeaways
- BC Hydro completed and energized the Treaty Creek Terminal, connecting Seabridge Gold Inc.'s KSM Project to the provincial hydroelectric grid.
- Seabridge says the terminal gives KSM reliable, clean, and economic hydroelectric power that lowers its carbon footprint and operating costs.
- Feasibility study preparations ramped up in Q3, with 2026 field programs completed.
- The 13-kilometer Upper Treaty Creek Access Road, which provides access to the saddle portal area of the Mitchell Treaty Tunnels, was completed on budget shortly after the third quarter ended.
- Seabridge posted Q3 net income of CA$6.7 million, compared with a CA$32.3 million net loss a year earlier, and invested CA$188.7 million in KSM during the first nine months of 2026.
- The company continues to work toward an earn-in joint venture for KSM with its preferred partner.
- Seabridge acquired the Sierra Madre gold-copper project in southern Wyoming in October.
KSM Switches On Hydro Power
BC Hydro has completed and energized the Treaty Creek Terminal (TCT) station, connecting Seabridge Gold Inc.'s (SEA:TSX; SA:NYSE) KSM Project to the provincial hydroelectric grid, according to the company's November 12 third-quarter report to shareholders.
The terminal was substantially completed on August 27, 2026, Seabridge said in a September 8 release, and was expected to be ready for service by November. Located on Highway 37, approximately 2 kilometers north of the entrance to KSM in northwestern British Columbia, the terminal connects the KSM Project to BC Hydro's Northwest Transmission Line. Seabridge considers the terminal critically important project infrastructure for future construction and operations at KSM.
The multi-year build of the TCT, regional system upgrades, and the tie-in to the transmission line made up the second phase of the Facilities Agreement between Seabridge and BC Hydro for construction power. The on-site work was done by BC Hydro's Indigenous partner, the Treaty Creek Limited Partnership (TCLP), a 50/50 venture between the Nisga'a Growth Corporation and the Tahltan Nation Development Corporation that was set up for the KSM Project. BC Hydro reports construction costs are in line with earlier forecasts. The terminal was formally turned over to BC Hydro's operations team in the third quarter of 2026, and final project closeout is scheduled for the fourth quarter.
"The Treaty Creek Terminal means KSM has access to reliable, clean and economic hydroelectric power which lowers KSM's carbon footprint and reduces its operating costs," Chair and CEO Rudi Fronk said in the September release.
Feasibility Push Gains Speed at KSM
Seabridge said the third quarter of 2026 continued the ramp-up in preparations for the KSM feasibility study, which it is working on with its prospective partner. Field programs were completed to collect geotechnical, metallurgical, geochemical, and environmental data. Preliminary mine planning, process plant layout, and site infrastructure planning were advanced. Work commenced on development of a project execution plan and on a 2027 early contractor engagement plan.
The company continued to execute an extensive site investigation program consisting of drill holes and test pits across the tailings management facility and the West Borrow areas during the quarter. Data collected during the 2026 field season will be used for the feasibility study as well as for future construction of critical works.
The 13-kilometer Upper Treaty Creek Access Road, which provides access to the saddle portal area of the Mitchell Treaty Tunnels, was completed on budget shortly after the third quarter ended. The road is being constructed by the Treaty Creek Limited Joint Venture between Lemare Construction and TCLP. Five camps were used during the 2026 field season, and the site peaked at more than 350 personnel in August. Hodder Camp was also expanded to support drilling activities. Engineering and planning work on the Coulter Creek Access Road and the Mitchell-Treaty Tunnels portal area continued. The site logged its highest annual work hours yet with zero lost-time incidents year to date.
Seabridge is targeting completion of the KSM feasibility study by the end of 2027. Preparatory work during the third quarter focused on trade-off studies and evaluations to establish the final project description.
Partner Talks Continue, Wyoming Added
Seabridge said in its report that it is continuing to work with its preferred partner on an earn-in joint venture for KSM and that the company is aligning expectations for the 2027 field program with that partner.
British Columbia's Environmental Assessment Office is reconsidering KSM's substantially started designation, which the project received in July 2024, following a June 8, 2026 BC Supreme Court decision. The 90-day period for written submissions by the Tsetsaut Skii km Lax Ha ended on September 28, 2026. A court hearing to settle the orders given in the June 8 decision took place on October 14, 2026, and that decision has not yet been released. Seabridge has provided additional information on work completed at KSM since the original designation was granted.
Chris Temple of The National Investor counts Seabridge among his current "core" recommendations.
Seabridge acquired the Sierra Madre Project in southern Wyoming in October 2026 from Orogen Royalties Inc. (OGN:TSXV; OGNNF:OTCQX) for US$300,000 cash and up to US$2.55 million in milestone payments. Orogen keeps a 2.5% net smelter return royalty on the existing claims. Seabridge believes Sierra Madre holds potential for a large, high-grade gold deposit with critical metal co-products.
The company reported a net loss of CA$32.3 million in the third quarter of last year, but turned a profit of CA$6.7 million, or CA$0.06 per share, in the third quarter of this year. Seabridge invested CA$188.7 million in the KSM Project during the first nine months of 2026 and had CA$56.3 million in cash at September 30. November 2, the company drew the remaining US$50 million of its US$100 million short-term loan from a strategic investor, fully utilizing the facility.
Newsletter Writer Keeps Seabridge a 'Core' Pick
Chris Temple of The National Investor counts Seabridge among his current "core" recommendations, and maintains an "accumulate" rating on the stock as of this date. Though he advised his members to sell part of their position (which had more than quadrupled since his initial recommendation) a while back to shelter some profits from the correction, he maintains that Seabridge longer-term is one of the most attractive equities to take advantage of the underlying, secular bullish moves for both gold and copper.
"The magnitude of its copper and gold resources/proven reserves at KSM are world-leading," Temple told Streetwise Reports.
Two of the analysts covering the company have rated the stock a "Buy." Most recently, RBC Capital Markets analyst Josh Wolfson reiterated his "Buy" rating on September 15, with a target price of CA$102.75, according to TipRanks. Before that, B. Riley Securities analyst Soundarya Iyer rated the stock a "Buy" on August 3, with a target price of CA$57.09.
Stonegate Capital Partners analyst Dave Storms set a US$72.28 target on August 20. He wrote that progress on KSM ownership and financing would move the stock more than resource growth, and he sees a joint venture as the next major catalyst.
Central Banks Keep Buying Gold
Gold fell as markets braced for a December rate hike from the Federal Reserve, but long-term buyers continued to purchase the metal. On November 13, 2026, at 12:43 p.m. ET, gold was trading at US$3,885.10 per troy ounce, according to Kitco, as it recovered from a 13-month low.
Long-term demand from central banks is steady. The World Gold Council reported that net central bank buying in the third quarter of 2026 was 321 tonnes, up 42% from a year earlier and the highest quarterly total since late 2024, according to Kitco. Despite lower gold prices in October, China continued to buy, adding about 26 tonnes of gold to its reserves during the month, Exchange Rates UK reported.
Major banks see higher prices ahead for gold. Even after cutting its forecast, Goldman Sachs sees gold rising about 16% over the next 12 months, to US$4,700 an ounce, according to the same report. UBS expects gold to rise over the next 12 months, supported by central bank buying, reserve diversification, elevated government debt, and geopolitical uncertainty. Its strategists expect structural buyers to set a floor near US$4,000 an ounce. November through January has also historically been a stronger period for gold, according to a StoneX analysis.
Seabridge's management believes the current pessimism toward gold won't last. In the company's Q3 report, management wrote, "We think there will likely be no rate hike in December, the narrative weighing on gold will break, the dollar will fall and gold will recover its momentum."
Copper adds a second tailwind for KSM, a gold-copper project. Copper reached an all-time high of US$6.85 per pound in September 2026, according to Trading Economics. Supply is tight as well. Chile's third-quarter copper output fell to a two-decade low, Procurement Resource reported.
Ownership and Share Structure1
Institutions hold about 44.40% of Seabridge, while Management and insiders own approximately 20.00%, with retail investors accounting for the balance.
The company has roughly 107.87 million shares outstanding and a market capitalization of about CA$3.55 billion.
No verified insider open-market buys or sells were found for the last six months.
No current warrants were found. Public records show one historical share restructure.
Common Questions from Investors
What is the Treaty Creek Terminal?
It's a BC Hydro station on Highway 37, about 2 kilometers north of the KSM entrance, that connects the project to BC Hydro's Northwest Transmission Line. The Treaty Creek Terminal is a BC Hydro facility on Highway 37, approximately 2 kilometers north of the KSM entrance. It was energized on August 27, 2026. As of the company's November 12 report, BC Hydro contractors were completing controls, communications, testing, and finishing work.
Why does grid power matter for KSM?
Chair and CEO Rudi Fronk said the terminal gives KSM access to reliable, clean, and economic hydroelectric power, which lowers its carbon footprint and operating costs. Seabridge calls it critically important infrastructure for future construction and operations.
Where does the KSM feasibility study stand?
Seabridge completed its 2026 field programs to collect geotechnical, metallurgical, geochemical, and environmental data. It advanced trade-off studies and preliminary engineering work and is targeting completion of the KSM feasibility study by the end of 2027.
Has Seabridge found a partner for KSM?
Seabridge is continuing to work on an earn-in joint venture with its preferred partner and is aligning expectations for the 2027 field program with that partner. No agreement has been announced.
What is happening with KSM's substantially started designation?
British Columbia's Environmental Assessment Office is reconsidering the designation after a June 8, 2026 BC Supreme Court decision. A court hearing to settle the ruling's orders took place on October 14, and that decision has not yet been released.
How is Seabridge funding its work?
Seabridge had CA$56.3 million in cash at September 30. On November 2, it drew the remaining US$50 million of its US$100 million short-term loan from a strategic investor, fully using the facility.
What do analysts and newsletter writers say?
Chris Temple of The National Investor keeps Seabridge among his "core" recommendations, with an "accumulate" rating.
RBC Capital Markets and B. Riley Securities both rate the stock a "Buy," and Stonegate Capital Partners has a US$72.28 target.
| Want to be the first to know about interesting Gold investment ideas? Sign up to receive the FREE Streetwise Reports' newsletter. | Subscribe |
Important Disclosures:
- Seabridge Gold Inc. is a billboard sponsor of Streetwise Reports. The company pays a monthly sponsorship fee of US$3,000–US$6,000 for banner advertising and an enhanced company profile page. Streetwise Reports’ editorial content is fully independent and is not influenced by sponsorship.
- As of the date of this article, officers, contractors, shareholders, and/or employees of Streetwise Reports LLC (including members of their household) own securities of Seabridge Gold Inc. and Orogen Royalties.
- Steve Sobek wrote this article for Streetwise Reports LLC and provides services to Streetwise Reports as an employee.
- This article does not constitute investment advice and is not a solicitation for any investment. Streetwise Reports does not render general or specific investment advice and the information on Streetwise Reports should not be considered a recommendation to buy or sell any security. Each reader is encouraged to consult with his or her personal financial adviser and perform their own comprehensive investment research. By opening this page, each reader accepts and agrees to Streetwise Reports' terms of use and full legal disclaimer. Streetwise Reports does not endorse or recommend the business, products, services or securities of any company.
For additional disclosures, please click here.
1. Ownership and Share Structure Information
Ownership percentages, named holders, share count, market capitalization, and the 52-week range for Seabridge were compiled from the company's public filings and investor materials, exchange notices, insider-trade reports (SEDI / equivalent), and third-party data providers. Figures are as of 2026-10-28 unless a source was dated earlier. Pie slices are normalized to 100% of basic shares outstanding; retail is the residual after disclosed institutions, management, insiders, and strategic holders. Warrant terms are current outstanding series only. Restructures are historical consolidations, splits, and symbol or name changes. Insider buying and selling covers open-market trades from 2026-04-28 through 2026-10-28 and excludes option exercises. These are public-source estimates and can differ from a later official register.