Cabral Gold Inc. (CBR:TSX.V; CBGZF:OTCMKTS) provided a construction update on its phase 1 gold-in-oxide heap leach project located in the Cuiu Cuiu gold district in Brazil, according to a March 5 release.
As of now, the construction activities are 54% complete, with 71% of the project costs already committed under contract, the company said. The project is progressing on budget and is on track with its timeline, aiming for plant commissioning in the third quarter of 2026 and expecting to start commercial production in the fourth quarter of the same year.
The detailed engineering phase is proceeding smoothly, and the procurement of major plant equipment is more than 90% complete. The acquisition of the remaining equipment is expected to be finalized later this month. The construction team, along with the contractors, has accumulated a total of 93,625 work hours in 2026 without any lost-time incidents.
"Our construction team continues to make excellent progress in executing on the 12-month construction program for our phase 1 gold-in-oxide heap leach project at Cuiu Cuiu," President and Chief Executive Officer Alan Carter said. "Our team has demonstrated resilience and strong technical capability in successfully dealing with the challenges encountered to date. We have put behind us the uncertainty normally associated with significant earthworks of a construction project, and we are now focused on above ground construction and plant erection, which is less dependent on weather conditions."
Carter continued, "The execution of the project plan is proceeding on budget and to schedule, targeting commissioning of the plant in the third quarter of 2026, followed by commercial production at Cuiu Cuiu in the fourth quarter of 2026."
Currently, the project site hosts 283 employees and contractors, excluding the off-site Ausenco Brazil engineering team and members of Cabral's exploration team, Cabral said in the release. Notably, all personnel on site are Brazilian, with 70% hailing from the state of Para. The infill drilling of the MG oxide starter pit, which is crucial for the first 12 months of operation, is 75% complete. This drilling will soon contribute to a detailed mine design, laying the groundwork for mining activities set to commence in mid-2026.
Co. Making Significant Progress
The ongoing detailed engineering efforts and construction execution drawings are advancing ahead of schedule, ensuring that these activities do not delay the project's critical path, the company said.
Cabral is making significant progress on Cuiu Cuiu, with several key priorities currently underway. These include completing P&IDs and detailed designs for wet systems post-heap leach pads, conducting geotechnical studies to support the design of spent ore pile and waste rock facilities, and finalizing design and execution drawings for the construction of heap leach pads scheduled for the second quarter of 2026.
In terms of procurement and delivery, over 90% of the equipment for the major plant has been procured, the company said. Notable long-lead items such as the adsorption, desorption, and recovery (ADR) plant, the mineral sizer, and various conveyor systems are in advanced stages of manufacturing. The ADR plant is nearing the final stages of assembly at Como Engineering in Perth, Australia, and is set for a dry commissioning program in March before being disassembled for shipment to the site. Local suppliers are progressing with the manufacturing of steel structures, including the run-of-mine ore bin and its support structures, expected on-site by mid-March.
Infrastructure improvements are also advancing, with the permanent mine camp area cleared and leveled, and construction that began in January 2026 is on track for completion by the end of March, Cabral noted. The project's earthworks on the production plateau and most concrete foundations are 95% complete, with the final water and solution storage ponds nearing completion. A nine-meter-high mechanically stabilized earth retaining wall for the ROM ore reception area has also been completed.
The project development timeline remains on schedule, with plant commissioning expected in Q3 2026 and commercial production anticipated in Q4 2026, the release said. The workforce, comprising entirely of Brazilians, with 70% being local residents from the state of Para, is set to transition from earthmoving to plant erection and construction in the coming months.
Looking ahead, the project will continue to focus on key development milestones including an infill drilling program at the MG pit in the first quarter of 2026, the arrival of major equipment on-site in the first and second quarters, the arrival of the ADR plant in Q3, followed by plant construction, commissioning, and the ramp-up to commercial production by the end of 2026.
Cabral Vigorously Pushes Exploration, Analyst Says
The Phase 1 HL project is anticipated to produce approximately 15-20,000 ounces of gold per year, according to an updated research note by Paradigm Capital Analyst Don Blyth on March 5. While this production scale is relatively modest, it is expected to generate significant pre-tax cash flow, particularly with gold prices at around US$5,000 per ounce, potentially reaching CA$45-CA$60 million annually. This phase is designed to establish Cabral as a self-funding explorer-developer, setting the stage for the "Phase 2" development plan, which would involve milling the hard/fresh rock mineralization.
Cabral is also vigorously pursuing exploration, with three drill rigs currently operational at the project. Continued positive drill results could potentially lead to a doubling of exploration activities in 2027. The next Mineral Resource Estimate (MRE) for the Cuiú Cuiú project, expected later in 2026, is projected to confirm at least 2 million ounces of global mineral resources.
In terms of human resources, the project employs 283 workers, all of whom are Brazilian, with 70% being local residents from the state of Para. The workforce is expected to transition from earthmoving to plant erection and construction in the upcoming months, which will be the primary focus of the project's next phases.
"In our opinion, Cabral remains an obvious takeover candidate for G Mining Ventures with its Tocantinzinho mine operating (literally) next door to the Cuiú Cuiú project," Blyth wrote. "However, Cabral is advancing its Phase 1 HL project, continuing to grow resources and demonstrate a larger standalone project not dependent upon a takeover to create shareholder value."
Significant Cash Flow by Year's End?
The project is tracking well against its budget and timeline, with plant commissioning expected in Q3 2026 and commercial production anticipated in Q4 2026, according to The Gold Advisor Senior Analyst Jeff Valks on March 5.
It has transitioned from the intensive earth-moving phase, which is now 95% complete, to above-ground construction and plant installation. These stages are less affected by weather, marking a significant shift in the construction process. Carter noted that the team has effectively navigated the challenges associated with major earthworks and is now focusing on erecting the plant and developing surface infrastructure.
While construction updates may not capture headlines like drilling results, they are crucial indicators of steady progress towards production — a critical phase in the mining development cycle that both the market and investors closely monitor.
With the project more than halfway through construction and on track according to its pre-feasibility study, Cabral Gold is well-positioned to transition from exploration to generating significant cash flow by the year's end.
"Looking at the U.S. chart, the stock is up slightly today and has climbed 207% over the last year," Valks noted. "It’s a Buy but accumulate on down days. I hold a long position; Jeff Clark maintains full weighting and is not taking profits."
The Catalyst: Gold Gets Its Footing Again
The gold market has recently seen a resurgence, climbing back above US$5,100 an ounce as new data from the U.S. labor market indicates significant weakness, potentially prompting the Federal Reserve to implement deeper interest rate cuts later this year, reported Neils Christensen for Kitco News on March 6.
According to the latest report from the Bureau of Labor Statistics released on Friday, U.S. nonfarm payrolls decreased by 92,000 jobs in February, a figure that starkly missed the anticipated gains of around 58,000 jobs projected by economists. Concurrently, the unemployment rate edged up to 4.4%, a slight increase from January’s 4.3%, contrary to expectations that it would remain steady.
Despite the ongoing turmoil in the Middle East, the gold market had been struggling to maintain its status as a safe-haven asset. However, the recent disappointing employment figures have spurred a renewed interest in gold. Spot gold was last seen trading at US$5,128.50 an ounce, marking an increase of nearly 1% on the day.
The employment report also highlighted further economic concerns with significant downward revisions to previous data. December’s employment figures were adjusted to reflect a loss of 17,000 jobs, a revision from the previously estimated gain of 65,000 jobs. Similarly, January’s figures were revised down to 126,000 from an initial estimate of 130,000 jobs.
On a positive note, the report indicated that wages are on the rise, with average hourly earnings increasing by 0.4% last month to $37.32, slightly above the 0.3% increase forecasted by economists. Over the past year, average hourly earnings have seen a growth of 3.8%.
Jeffrey Roach, Chief Economist for LPL Financial, commented on the labor market's performance, noting that after unimpressive job gains in 2025, the labor market appears to be stagnating. "The three-month average is 6,000 and the six-month average is negative for the fourth time in five months," he observed.
Looking forward, Roach anticipates a rise in the unemployment rate and suggests that while the Federal Reserve might not adjust rates until June, a quicker deterioration in the labor market could prompt an earlier rate cut, potentially as soon as April 29.
In a recent analysis by Crystal Kim for Investopedia, dated March 5, it was noted that gold, often seen as a hedge against geopolitical turmoil, has unexpectedly deviated from its traditional role. Amidst the ongoing conflicts in the Middle East, the price of spot gold dropped by about 1.6% on Thursday, closing at approximately US$5,060 per troy ounce. Similarly, investment vehicles that focus on precious metals and mining stocks, such as the SPDR Gold Trust (GLD) and the VanEck Gold Miners ETF (GDX), are also poised to conclude the week with losses. Silver prices have seen a decline as well.
Market experts point to several reasons behind gold's surprising behavior. Notably, there has been a robust buying spree over the past year, with investors treating gold more as a speculative asset rather than a stable safe haven. Furthermore, recent military actions against Iran have pushed oil prices higher, raising concerns about potential inflation increases. This economic shift might prompt the Federal Reserve to hold off on reducing interest rates in the near future. Additionally, a strengthening U.S. dollar, which generally inversely affects gold prices, has also contributed to the downturn.
Streetwise Ownership Overview*
Cabral Gold Inc. (CBR:TSX.V; CBGZF:OTCMKTS)
Despite its reputation as a dependable asset in uncertain times, gold has not upheld the expected level of stability for investment portfolios amid the escalating Middle East tensions. Stephen Dover from the Franklin Templeton Institute discussed this trend in a CNBC interview, stating, "What you're seeing is things that have run up a lot maybe not run up as much as they had before." This comment underscores the shifting dynamics in investor response to gold in light of the recent geopolitical developments.
Ownership and Share Structure1
About 6% of the company is owned by insiders and management, while institutions own about 14%. The rest is retail.
Major shareholders include AMS Asset Management with 5.85%, Aegis Financial Corp. with 4.80%, the CEO, Carter, with 4.7%, and Director Lawrence Lepard with 1.13%.
It has 277.99 million shares outstanding and a market cap of CA$236.29 million. It trades in a 52-week range of CA$0.24 and CA$0.98.
| Want to be the first to know about interesting Gold investment ideas? Sign up to receive the FREE Streetwise Reports' newsletter. | Subscribe |
Important Disclosures:
- Steve Sobek wrote this article for Streetwise Reports LLC and provides services to Streetwise Reports as an employee.
- This article does not constitute investment advice and is not a solicitation for any investment. Streetwise Reports does not render general or specific investment advice and the information on Streetwise Reports should not be considered a recommendation to buy or sell any security. Each reader is encouraged to consult with his or her personal financial adviser and perform their own comprehensive investment research. By opening this page, each reader accepts and agrees to Streetwise Reports' terms of use and full legal disclaimer. Streetwise Reports does not endorse or recommend the business, products, services or securities of any company.
For additional disclosures, please click here.
1. Ownership and Share Structure Information
The information listed above was updated on the date this article was published and was compiled from information from the company and various other data providers.












































